A two-story residential addition in Walnut Creek has posed some planning and technical challenges over the autumn and winter months. Bridging over a demolished swimming pool structure demanded (19) 24-foot deep concrete piers and 18x24” grade beams in a side yard along an angled property line with a 10-foot Sanitary District easement.
Now that the weather has afforded the opportunity, it’s time for foundations.
Friday morning, it all passed inspection. By Monday afternoon , it’ll all be covered with concrete.